Admin Report for December 5, 2017
Dec05

Admin Report for December 5, 2017

Financial Report First Quarter:  The revenue and expenditure reports for July 1 to September 30, 2017 are in your material. For the first quarter of the year the county has used 24.32% of the budget. Significant Projects and Activity Courthouse Renovation:  The bid documents should be ready by March 1, 2018 and bids due around April 1, 2018. Construction is projected to start May 1st. Animal Shelter:  Detailed plans and specifications...

Read More
Admin Report for November 21, 2017
Nov21

Admin Report for November 21, 2017

Financial Report First Quarter Report:  The revenue and expenditure reports for July 1 to September 30, 2017 are in your material. For the first quarter of the year the county has used 24.32% of the budget. Significant Projects and Activity Courthouse Renovation:  The bid documents should be ready by March 1, 2018 and bids due around April 1, 2018. Construction is projected to start May 1st. Animal Shelter:  Detailed plans and...

Read More

Admin Report for November 7, 2017

Financial Report Year End:  The Year End reports for fiscal year ending June 30, 2016 are in your material for tonight. SPLOST and LOST:  SPLOST collections for October were $698,124.08 which is a $128,951.24 increase (22.66%) over the same period in 2016. The collections for October 2015 were $697,997.61. LOST collections for October were $484,150.21 which is an increase of $89,380.75 (22.64%) over October 2016. The LOST collections...

Read More
Admin Report for October 17, 2017
Oct23

Admin Report for October 17, 2017

Significant Projects and Activity Courthouse Renovation:  We remain on schedule for the completion of bid documents and due dates for bids. The dates remain such that the bid documents will be ready by January 30, 2018 and bids due March 6, 2018. Animal Shelter:  I met with the Architects on Thursday, October 5th to review detailed drawings. A meeting is set tomorrow afternoon with Animal Control and others to review the plans. We are...

Read More
Admin Report for October 3, 2017
Oct04

Admin Report for October 3, 2017

Financial Update SPLOST and LOST:  SPLOST and LOST Collections were up again in September. SPLOST collections were up $40,506.31 over this period last year which is a 6.39% increase. LOST collections were up $28,089.15 over September 2016 which is also a 6.39% increase. This follows 11.9% increases last month. Looking at August and September, collections are up a total $80,348.99 compared to these months last year. Significant...

Read More
Admin Report for September 19, 2017
Sep28

Admin Report for September 19, 2017

Financial Update Millage Rate:  There is a special called meeting for Monday, September 25, 2017 at 6:00 p.m. to set the millage rate. I expect Finance will expect a rollback from 9.853 mils to 9.828 mils. Significant Projects and Activity Courthouse Renovation:  The Architects have provided a preliminary schedule for the completion of bid documents and due dates for bids. For the Courthouse renovations and judicial building...

Read More